Survey Dynamics have been contracted to provide survey for the upgrade of the RAAF Curtin Learmonth Base, located 30km south of Exmouth. The upgrades include improvements to runway and apron capacity, fuel supply and storage, accommodation and security. More specifically, Survey Dynamics have to-date provided survey for the construction of an asphalt plant, concrete plant, site camp and site office to service the construction project. Upgrade works have commenced on the widening of the highway intersection and internal roads and survey has also been provided for the location of utilities, including fibre optics, water mains, fuel line and HV/LV. Works have also begun for taxiways and aprons.

Survey methods include; verticality survey of structures (lights, sports courts nets, shade sails), bolt and screw pile Setout and ascon, earth works, clearing set out, establishing control, machine control, detail surveys, concrete works.