Principal:               Covalent Lithium
Client:                     Decmil
Location:                Mount Holland, Western Australia
Status:                    Completed

This project involves the construction of a 113km road linking the Covalent Lithium Mine with Great Eastern Highway. Survey Dynamics will be undertaking the following works:

  • Drone flights of the 113km road, borrow pits, stockpiles and side roads
  • Control network over the length of the job
  • Machine control for upwards of 50 machines at peak construction
  • Mass haul volume calculations with over 1 million cubic metres of soil to be used during construction.

The project commenced in September 2023 and is expected to take 2 years to complete. Survey Dynamics is expected to have a crew of 8-10 people at the height of construction.